The robust performance comes after MICT achieved record volume and productivity with its first year to date two million TEU move last December.
"Yard utilisation at the terminal remains optimal. The mechanisms we developed together with the Philippine government and other stakeholders in 2014 continue to work, resulting in the easing of traffic in Metro Manila despite inadequate trade infrastructure," explains Christian R Gonzalez, ICTSI senior vice president and head of Asia Pacific region and MICT.
As of May, yard utilisation at the MICT remained at 61 per cent or well below the 70 per cent ideal percentage. During the same month, average crane productivity hovered at 32 moves per hour. These numbers underscore the terminal's strong performance despite the uptick in container volume as global trade continues to rebound, according to an ICTSI statement.
Last year, the MICT achieved a milestone with its first year to date two millionth TEU move, triggering a multi-billion peso capacity improvement commitment with the Philippine Ports Authority (PPA) that requires ICTSI to commission five neo-Panamax quay cranes, 12 reach stackers, and build two new berths by 2020. The expansion and capacity improvement will enable the MICT to service bigger ships, which is now becoming the trend in global container trade.
"We are entering the era of larger ships. We need to adapt and stay competitive by enhancing our capabilities, which is something that we have already started," adds Mr Gonzalez.
As the country enters the second half of the fiscal year, volume is expected to surge, with imports starting to arrive ahead of the holiday season. Historical data from the PPA also show consistent MICT volume growth since 2015, with productivity and utilisation staying proportionally healthy all throughout.
"The congestion problem in the Port of Manila in 2014 provided us with the opportunity to further improve our operations at the MICT. We resolved the issue by putting in place new technologies that would not only upgrade the terminal, but would make MICT a sustainable business factoring in the quality of life of our hinterland communities and immediate environs. We've engaged all port stakeholders in resolving the issue," says Mr Gonzalez.
"In 2014, the root cause of the port congestion was the truck ban that limited truck movement in the city's major thoroughfares. We simply couldn't get the containers out of the terminal. We needed to think outside of the dock - and that's how we came up with the Terminal Appointment Booking System (TABS). We looked for a solution to the problem outside the port," he said.
Under TABS, trucks arrive at the terminal according to the booked slot schedule, which the system evenly distributes throughout the day. This system helped reduce the number of trucks on the road without limiting the movement of cargo.
To further ease container movement and ensure seamless operations at the MICT, ICTSI implemented capacity and facility upgrades. Terminal utilisation improved since 2015 after the completion of Yard 7, which increased the terminal's capacity by 18 per cent from 2.5 million to 2.75 million TEU. Yard 7 is part of MICT's PHP5 billion (US$99 million) expansion project.
"Yard utilisation at the terminal remains optimal. The mechanisms we developed together with the Philippine government and other stakeholders in 2014 continue to work, resulting in the easing of traffic in Metro Manila despite inadequate trade infrastructure," explains Christian R Gonzalez, ICTSI senior vice president and head of Asia Pacific region and MICT.
As of May, yard utilisation at the MICT remained at 61 per cent or well below the 70 per cent ideal percentage. During the same month, average crane productivity hovered at 32 moves per hour. These numbers underscore the terminal's strong performance despite the uptick in container volume as global trade continues to rebound, according to an ICTSI statement.
Last year, the MICT achieved a milestone with its first year to date two millionth TEU move, triggering a multi-billion peso capacity improvement commitment with the Philippine Ports Authority (PPA) that requires ICTSI to commission five neo-Panamax quay cranes, 12 reach stackers, and build two new berths by 2020. The expansion and capacity improvement will enable the MICT to service bigger ships, which is now becoming the trend in global container trade.
"We are entering the era of larger ships. We need to adapt and stay competitive by enhancing our capabilities, which is something that we have already started," adds Mr Gonzalez.
As the country enters the second half of the fiscal year, volume is expected to surge, with imports starting to arrive ahead of the holiday season. Historical data from the PPA also show consistent MICT volume growth since 2015, with productivity and utilisation staying proportionally healthy all throughout.
"The congestion problem in the Port of Manila in 2014 provided us with the opportunity to further improve our operations at the MICT. We resolved the issue by putting in place new technologies that would not only upgrade the terminal, but would make MICT a sustainable business factoring in the quality of life of our hinterland communities and immediate environs. We've engaged all port stakeholders in resolving the issue," says Mr Gonzalez.
"In 2014, the root cause of the port congestion was the truck ban that limited truck movement in the city's major thoroughfares. We simply couldn't get the containers out of the terminal. We needed to think outside of the dock - and that's how we came up with the Terminal Appointment Booking System (TABS). We looked for a solution to the problem outside the port," he said.
Under TABS, trucks arrive at the terminal according to the booked slot schedule, which the system evenly distributes throughout the day. This system helped reduce the number of trucks on the road without limiting the movement of cargo.
To further ease container movement and ensure seamless operations at the MICT, ICTSI implemented capacity and facility upgrades. Terminal utilisation improved since 2015 after the completion of Yard 7, which increased the terminal's capacity by 18 per cent from 2.5 million to 2.75 million TEU. Yard 7 is part of MICT's PHP5 billion (US$99 million) expansion project.