After multiple delays the 'Peter Pan' finally left Bremerhaven on May 28 at 11 p.m. for trials after having been enlengthened at German Dry Docks (GDD) by a 30 meter-section during the last five months. If the tests are successful, the ferry was expected to return into the Travemünde–Trelleborg run during this week, but three months later than planned. The ship had entered dock 5 end of December 2017 and was to be redelivered end of February. But especially trouble with the electircal installations caused a significant delay. German report with photo: https://nord24.de/bremerhaven/peter-pan-laeuft-zur-probefahrt-aus More on the issue: https://www.forum-schiff....
WORLD SHIPPING
29 May 2018 - 10:35
Ferry starts trials three months behind schedule
After multiple delays the 'Peter Pan' finally left Bremerhaven on May 28 at 11 p