Aircraft Carrier INS Vikramaditya to Start Sea Trials in Four Months
About 100 days left to May 25 when Project 11430 aircraft
carrier INS Vikramaditya will start sea trials. Up to 3,000 shipwrights
and experts daily work on the carrier modernized at JSC Sevmash
Shipyard. Friday, 27.Jan.2012, 16:54 (GMT+3)
About 100 days left to May 25 when Project 11430 aircraft
carrier INS Vikramaditya will start sea trials. Up to 3,000 shipwrights
and experts daily work on the carrier modernized at JSC Sevmash
Shipyard. No wonder that labor power is such significant â only 3.5
months left to sea trials, and there is much work to be done. Igor
Leonov who is in charge of the shipâs delivery told the yardâs newspaper
Korabel about achieved results and plans for the winter.
âThe most important task for nearest few days is normal starting
of four stern boilers. Two boilers have already passed steam test. The
rest of boilers will be tested this week. According to work schedule, on
Jan 26 Vikramaditya is receiving own steam generated by portside
boilers for the first time. The steam is used for operation of the
shipâs mechanisms. In a few days weâre going to start autonomous work of
the starboard boilers, and that will mean the beginning of full-fledged
mooring trialsâ, said I. Leonov. As for him, bow boilers will be brought into energy mode late January. The ship must be ready to move by boilers early April.
The next objective for January is shipyard trials of steering system,
completion of washing and testing of hydraulic system, and assembling
of high-pressure air system. Those are the most important
general-purpose shipboard systems, and their readiness affects trial
periods of many other systems, for one, arresters.
Adjustment works on radioelectronics are to be finished in February
and then dual matching will start. Dozens of adjusters representing
contracting parties are working on the ship. So far, there are no doubts
that coastal tests of radioelectronics will be completed late March or
early April. Finally, the tests will be finished at sea.
Bow and stern elevators will be assembled till the end of Jan, and then their mooring trials will start. âIn mid-February weâre going to test aircraft-related systems such as retaining and arresting devicesâ, Leonov said. âIn
March we will face a very critical task â taking on board 700 cubic
meters of aircraft fuel. By that time, all hot works must be over, and
ramified fuel feed system must be assembled. Then will start thorough
flushing of fuel pipes and tanks. Requirements for fuel cleanliness are
very high; it must not contain foreign particles larger than 3-5
microns. Along with that we will test aviation fuel stations. All those
works will take about two monthsâ, concluded the interviewee.
According to I. Leonov, the most critical work is finishing of
service utility premises. This issue is upon maximal attention, since
Russian crew will settle in the ship by Feb 23. A number of living
quarters and ablutions in the shipâs bows must be prepared by that time.
âNew bonus plan for workers and specialists was put in action in
December. Its effectiveness surpassed all expectations â the monthâs
schedule was completed in-full, and this trend goes onâ, pointed out Leonov.