Delivery-Acceptance act for the second multipurpose salvage
vessel of MPSV07 project “SPASATEL KAVDEJKIN” was signed on August 19th, 2013. Under the terms of the contract the Act signing took place in
Murmansk.The vessel “SPASATEL KAVDEJKIN” departed Saint-Petersburg port on
August 7th and sailed around Scandinavia and back to Murmansk port on
August 17th, 2013.The owner of the vessel is the Direction of State Contractor of
Marine Transport Development Program of the Federal Marine and River
Transport Agency of Ministry of Transport of the Russian Federation.The project MPSV07 is developed by Marine Engineering Bureau-Design-SPb, JSC.Nowadays, the vessels of MPSV07 project are the biggest and the most
significant vessels built at the expense of Federal Target Program
“Russian Transport System Development (2010-2015)”. These vessels have
unlimited navigation area including Northern Sea Route.Key Features:
Overall length - 73.0 m
Overall width - 16.6 m
Depth - 6.7 m
Working drafts - 4.0 - 5.1 m
Power plant - 4 MW
Full speed - 15 knots
Mooring pull - 70 t
Endurance - 20 days
Crew - 20 people
Designated rescued - 81
Overall length - 73.0 m
Overall width - 16.6 m
Depth - 6.7 m
Working drafts - 4.0 - 5.1 m
Power plant - 4 MW
Full speed - 15 knots
Mooring pull - 70 t
Endurance - 20 days
Crew - 20 people
Designated rescued - 81